Open Submittals
- Select the project.
- Open Submittals from the sidebar.
Submittal Log
The log lists every submittal with:- Number and revision
- Spec section and title
- Type (shop drawing, product data, sample, mock-up, etc.)
- Responsible contractor
- Submittal coordinator
- Reviewer
- Status and due dates
Create a Submittal
- Select Create Submittal.
- Enter Title, Spec Section, and Type.
- Assign the Responsible Contractor (subcontractor).
- Assign the Submittal Coordinator (typically the GC).
- Assign the Reviewer (design team).
- Set required and forecast dates.
- Save the submittal.
Review Workflow
The standard workflow has two review steps:- Submittal Coordinator Review — the GC reviews for completeness and forwards to design.
- Design Review — the design team reviews and returns one of:
- Approved (No Exceptions Taken)
- Approved as Noted
- Revise and Resubmit
- Rejected
- For Information Only
Revisions
If a submittal returns as Revise and Resubmit:- The subcontractor uploads a new revision.
- The revision number increments (Rev 1, Rev 2).
- The review workflow restarts.
Status
- Pending Submission
- Submitted to Coordinator
- Submitted to Reviewer
- Returned
- Closed